Background

The development of MUFC involved construction of two new cantilever roof structures above the new Quadrant seating.

The Challenge

Due to the roof’s design, access was needed below roof level to install the steel purlins and roofing sheets.

Scaffolding from lower level was not an option.

DIS Solution

Corner platform assembled and craned into place to allow ‘sump’ construction.

Sump platform followed by two larger main platforms craned into place.

Platforms removed by deconstructing while suspended.

Denholm Industrial
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.