RFA Mounts Bay

Spanning
15 tanks in
only 9 weeks

Background

Significant volume of tank blasting and painting to undertake on docking of vessel 19,910m².

The Challenge

Complete the works spanning 15 tanks in only 9 weeks from a standing start.

Mobilise and create an experienced delivery team.

50 experienced marine blasters and painters from our commercial operation.

600 tonnes of Abrasive blast media.

13,000 litres of paint applied.

DIS Solution

Careful planning and daily progress meetings with client.

Use of very experienced workforce and management team.

Working 24/7 over the 9-week duration.

Working with client and ship to overcome issues and challenges.

Denholm Industrial
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.