Denholm Industrial Logo
  • Call us on: +44 (0) 1935 420 081
  • Email us
  • Services
    • Close
    • Services
    • Scaffolding and Access
      • Close
      • Scaffolding and Access
      • Fall Prevention System
      • Plettac Metrix
    • Containment and Encapsulation
    • Metal Surface Preparation
    • Protective Coatings
    • Industrial Cleaning
    • Floor Surface Preparation
  • Sectors
    • Close
    • Sectors
    • Construction and Demolition
    • Infrastructure
    • Marine
    • Defence
    • Heritage
    • Process and Energy
  • Accreditations
  • Profile
    • Close
    • Profile
    • About Us
    • Our History
    • Our Ethos
  • Case Studies
    • Close
    • Case Studies
    • Construction and Demolition
      • Close
      • Construction and Demolition
      • Beckley Court Student Accommodation
      • NatWest Tower Demolition
    • Marine
      • Close
      • Marine
      • Dockyard Water Control Barriers Refurbishment
      • Portsmouth Jetty Upgrade
      • Crane 399 Refurbishment
    • Defence
      • Close
      • Defence
      • Industrial Cleaning at BAE Scotstoun
      • New Build Offshore Patrol Vessels
      • Vanguard Class Submarines
    • Infrastructure
      • Close
      • Infrastructure
      • Bidston Moss Viaduct Strengthening
      • Bidston Moss Viaduct Metal Preparation
      • Forth Road Bridge Refurbishment
      • Vox Studios Office Fit-Out
    • Heritage
      • Close
      • Heritage
      • Clifton Cathedral Roof Covering Renewal
      • Canford Road Bridge
    • Process and Energy
      • Close
      • Process and Energy
      • First Outage at Energy from Waste Plant
  • News
  • Vacancies
    • Close
    • Vacancies
    • Regional Office Administrator - Glasgow
    • Quantity Surveyor, Glasgow (Clyde)
    • HSEQ Advisor - Barrow-in-Furness
    • Painting Supervisor - Glasgow
    • Quality Inspector (Coatings) - Glasgow
    • Scaffolders - Elite Scaffolding, Yeovil
    • Painting Apprenticeships - Glasgow
    • HSEQ Advisor - Portsmouth
    • Industrial Painting Personnel - Glasgow
    • Quality Inspector (Coatings) - Portsmouth
    • Scaffold Apprenticeships - Plymouth
    • Scaffold Apprenticeships - Yeovil
    • Scaffolding and Access
    • Industrial Paint Estimator
  • Contact
    • Close
    • Contact
    • Locations
      • Close
      • Locations
      • Glasgow
      • Plymouth
      • Scunthorpe
      • Winchester
      • Yeovil
      • SES - Birmingham
      • ALPS - Sheffield
      • Elite Scaffolding - Yeovil
    • Head Office

Portsmouth Jetty Upgrade

  1. Home
  2. Case Studies
  3. Marine
  4. Portsmouth Jetty Upgrade
Client: Volker Stevin
Location: Royal Naval Dockyard, Portsmouth
Project: Refurbishment of the QEC 1920 jetty

Background

Built in 1920, the jetty at Portsmouth naval dockyard was the designated site for two Queen Elizabeth aircraft carriers currently under construction. The jetty had to be upgraded and strengthened to support the two 66,000 tonne vessels; this required the provision of suspended access to 5,000m2 of the underside of the concrete structure.

The Challenge

The requirement set by the client was to provide fully suspended access scaffold that could only be supported from the underside of the 600mm thick concrete deck. The scaffold was to be built as a light duty scaffold with a loading of 0.75kN/m2 with the ability to upgrade the scaffold as required and with minimal effort to a loading of 2.50kN/m2.

The working platform would be set approximately 2 metres below the underside of the jetty, putting the scaffold platform within the tidal zone twice per day.

A third restriction was, due to the amount of work required to the underside of the concrete deck, no horizontal tubes could be installed within 2 metres of the underside of the concrete deck.

Our Solution

The series of unique challenges required serious consideration for a scaffold that would be in place for over a year.  Before addressing the method of suspension of the scaffold, consideration was given to the type of decking to be employed.  Normal scaffold boards or steel staging would be required to be fixed in place. They would also be subject to additional loading from tide and wave action, as well as deterioration from marine algae, which would also cause unsuitable conditions underfoot after only a short period to those using the scaffold.

Denholm Industrial Services' solution was to install GRP open grate decking. This was lighter than conventional decking and was constructed with 22mm square openings to allow unrestricted flow of water during tidal conditions. The GRP also provided a non-slip surface throughout the period of occupation with no deterioration of the product. The GRP was secured with sacrificial ties so that in the event of a foreign object becoming trapped below the scaffold, only the decking would be displaced and the structural integrity of the scaffold frame would remain intact. As the deck was exposed by the outgoing tide the GRP was simply repositioned to allow works to continue.

With the decking solution in place Denholm Industrial Services worked closely with one of our suppliers to enhance an existing scaffold fixing by providing a single point support system. The fixing bracket used for the first time on this project was tested to 40kN and, when bolted directly into the underside of the concrete jetty, provided a loading of 15kN per location, installed on a 2m2 grid throughout the 5000m2.  During the development of the fixing, we were also able to demonstrate that this solution eliminated the requirement to lace tubes to the underside of the concrete deck from which the scaffold would be suspended.

Having satisfied the client that Denholm Industrial Services had achieved a viable set of solutions, the operations team - working with daily tides - employed installation techniques developed over years of marine experience to erect the scaffold.

Additional

Case Studies

  • Dockyard Water Control Barriers Refurbishment
  • Portsmouth Jetty Upgrade
  • Crane 399 Refurbishment

Denholm Industrial Group

  • Flag Secondary Denholm Industrial Services
  • SES RGB SES
  • Elite Scaffolding_white Elite Scaffolding
  • ALPS LOGO (White No Strapline) ALPS

Head Office

Denholm Industrial Services Limited
1 Barracks Close
Lufton
Yeovil
BA22 8RN
enquiries@denholm-industrial.com
+44 (0) 1935 420 081
  • Terms of Use
  • Privacy Policy
  • Cookie Policy
  • Modern Slavery Act Statement
Denholm Industrial Services Limited is part of The Denholm Group
Telephone: +44 (0) 1935 420 081 Email: enquiries@denholm-industrial.com
© Denholm Industrial Services Limited 2023. All rights reserved.

Website by Gecko Agency

Our site uses cookies to help give you the best online experience.
Please let us know if you are happy for us to use these cookies or if you wish minimum functionality only.

I decline